The staircase is almost done!
It just needs the rest of the spindles on the bottom part of the banister.
The painters came back today to start the final paint job. They will also be the ones who stain the stair treads and paint the risers.
Tomorrow, the cleaning team comes in to do a "rough clean." That basically means cleaning the windows, vacuuming up all the dust, cleaning the tubs/showers. They'll come back right before we close to do a detail clean that will have the house sparkling. The tub surround is also being delivered, and so are the logs for the fireplace.
Thursday or Friday, the appliances are being delivered and installed, which means the gas people can come out and set the propane tank and test the system. I'm SO excited to be able to cook with gas again!
We're on track to close late next week! I can hardly believe that the house is thatclose to being done!